Transport Asset Management Plan 2022 – 2027

Councillor Neil Poole - Conservative - Messingham

Foreword

by Councillor Neil Poole, Deputy Leader and Cabinet Member for Operations and Flooding

The highway network in North Lincolnshire comprises 1402 km of roads. With an asset value in excess of £1.72 billion (excluding land), it is the most valuable infrastructure asset owned by the council.

As a highway authority, the Council has a statutory duty to maintain the highway. We do so in the face of increasing pressures.

We manage the highway network on behalf of the travelling public, whether they are pedestrians, cyclists, bus operators, taxi operators, freight operators or car users. How we maintain our highway network impacts on the outcomes for our residents. Ensuring residents are: Safe, Well, Prosperous and Connected.

A Transport Asset Management Plan (TAMP) has been written to provide a summary of how we go about managing the maintenance of our highway assets.

The TAMP focussed on the following asset groups:

  • Carriageways
  • Footways
  • Cycleways
  • Street Lighting
  • Drainage
  • Structures (Bridges & culverts)
  • Traffic Management (Traffic Signals)
  • Street Furniture

The purpose of the Transport Asset Management Plan is to:

  • Formalise strategies for investment in highway asset groups
  • Define affordable service standards
  • Improve how the highway asset is managed
  • To assist in delivery of a better Value for Money highways service

The TAMP is a live document and we will continue to review and update our policy and processes in response to emerging best practice in this field.

This document presents the annual update on the policy and overview of the TAMP 2022-2027.

The following North Lincolnshire Council documents are essential components of the council’s approach to transport asset management and complement and support this plan;

  • H&P Quality Manual
  • Local Transport Plan 3
  • Highway Maintenance Strategy
  • Winter Maintenance Plan
  • Risk Management Strategy and Action Plan
  • Road Safety Strategy
  • Information Management Policy
  • Traffic Signs Policy
  • Street Lighting Policy
  • Code of Practice for Highway Inspections

Other reference documents;

  • CIPFA – Code of Practice on Transport Infrastructure Assets 2016
  • Highways Maintenance Capital Funding Self-Assessment Questionnaire for Incentive Funding
  • Highways Maintenance Funding Formula and Indicative Incentive Fund Allocations 2015-2020
Economy and Environment Plan Element Main Council Position(s) Responsible
TAMP Document

TAMP implementation and practice improvements

  • Council Cabinet
  • Elected Member (portfolio holder) responsible for Highways
  • Director responsible for Highways
  • Director responsible for Highways
  • Asset Manager (Assets & Infrastructure
TAMP document updating and reporting
  • Asset Manager (Assets & Infrastructure)
Finance and Valuation
  • Asset Manager (Assets & Infrastructure)
  • Council Finance Section
TAMP Data
  • Asset Manager (Assets & Infrastructure)
  • Highways UKPMs / data section (Asset Evaluation Team)
  • Council GIS section
TAMP Risk
  • Asset Manager (Assets & Infrastructure)
  • Council’s Corporate Risk section
Asset strategy options reports
  • Asset Owners

1. Introduction

This section provides a brief introduction to the Transport Asset Management Plan (TAMP) and identifies how it is aligned with other council documents.

Overview

The Government encourages councils to develop asset management plans for their infrastructure assets via the Highways Maintenance Efficiency Programme (HMEP).

The purpose of the Transport Asset Management Plan (TAMP) is to:

  • Formalise strategies for investment in highway asset groups
  • Define affordable service standards
  • Improve how the highway asset is managed
  • To assist in delivery of a better value for money highways service

Links to the Council Pan and Other Plans

This TAMP follows the principals laid out in the Council Plan 2022-25, as well as other council plans as illustrated.

The 2014 Local Transport Plan (LTP) sets out the transport policies for the council and indicates potential financial allocations for Integrated Transport and Highway Maintenance – these being the two funding streams within the LTP award. An Integrated Transport Strategy is in development of which a large part of that will be the Local Transport Plan. This was produced in October 2021. This is also being aligned with the Local Plan for North Lincolnshire.

Image showing how the Local Transport Plan, The Transport Asset Management Plan and the Network Management Plan interlock under the main Council Plan

The Network Management Plan (NMP) is produced to document our arrangements in respect of carrying out our network management duty in relation to the Traffic Management Act 2004. The NMP has a direct bearing on our way of working and the allocation of funding for management of the highway network.

The adoption of asset management for highway assets is an on-going process of the use of more structured management processes and adopting a long term planning approach.

The long term planning process requires the assimilation of all information, together with the whole life costs, for each and all of the assets being considered. These whole life costs include not only the ‘life cycle’ costs for each of the assets, but also the non-construction costs, income from the asset and externalities associated with the asset. This can be seen in the flow chart below.

Image showing the Council Plan priorities

2. Asset Description

This section outlines the size and extent of the asset that is included within this Management Plan.

Asset Group Element Quantity
Carriageway Road construction including lay-bys, bus lanes etc.

The carriageway group also includes:
Kerbs, line markings and studs, traffic calming features verges / vegetation, boundary fencing
– including tables, humps, chicanes etc., hard strip / shoulder /

1,406 km
Footways and
footpaths
Footway – adjacent to the carriageway 960 km
Footways and
footpaths
Public Rights of Way remote from the carriageway including byways, restricted byways,
bridleways and footpaths.The footway and footpaths group also includes;
Roadside signposts (207), waymark posts (1,593), small pedestrian bridges (192), stiles (212), gates (135), flights of steps (25), countryside car parks (7), Interpretive panels (10) and boardwalks (6)
534 km
Cycleways Cycleways – either on carriageways or shared with footways included in carriageway section n/a
Cycleways Cycleways – remote from the carriageway – included in carriageways and/or footways n/a
Structures Bridges 144
Structures Footbridges 5
Structures Culverts (large diameter piped drains under the road) 131
Structures Retaining walls 2
Structures Underpasses / subways 1
Street Lighting Lighting columns 24,378
Street Lighting Illuminated signs 1,230
Street Lighting Illuminated bollards and beacons 292
Street Lighting Feeder pillars (council owned) 160
Street Lighting Cabling for street lighting 142 km
Traffic Management
Systems
Signal installations at junctions 36
Traffic Management
Systems
Signal installations at pedestrian, pedestrian/cycle, pedestrian/horse crossings 17
Traffic Management
Systems
Variable message signs 15
Traffic Management
Systems
Vehicle activated signs 20
Traffic Management
Systems
Safety and speed camera equipment 1
Drainage Gullies 22,519
Drainage Manholes and catchpits 44,680
Drainage Piped drains 1,840 km
Drainage Pumping stations 19
Drainage Oil interceptors Unknown
Drainage Hydrobrakes

The drainage group also includes;
Balancing ponds, roadside ditches, swales, soakaways, inlets and outfalls etc

4
Street Furniture The street furniture group includes;
Vehicle safety fences, non-illuminated signs (warning, regulatory and local direction/information signs/posts), bollards,
pedestrian guardrail, street name plates, litter and grit bins, seating, bus stops (1,102), highway trees (approx 8,000) etc.

Some highway related assets are the responsibility of other council departments for maintenance purposes. The assets that are not covered by this TAMP are:

  • Scunthorpe bus station
  • Barton Interchange (bus station)
  • Car Parks
  • Public Transport Facilities

3. Community Requirements

This section describes information about the community’s requirements for the transport/highways asset. It outlines how this information is obtained and what it says in relation to community preferences.

The consultation process for LTP3 allowed us to build on the extensive consultation exercises we undertook with the community as part of the LTP2 midterm review. Various community groups and local forums were consulted. The key issues raised as part of this process related to winter maintenance & safety of roads in bad weather and the condition of footpaths. Both issues have been addressed over the early part of the Plan period.

More recently North Lincolnshire Council have taken part in the annual NHT Public Satisfaction Survey. This survey collects public perspectives on, and satisfaction with, Highway and Transport Services in Local Authority areas nationally. It is a unique, standardised, collaboration between Highway Authorities across the UK enabling comparison, knowledge sharing, and the potential to improve efficiencies by the sharing of good practice.

Further consultation opportunities with various stakeholders is planned as we develop the Integrated Transport Strategy.

Additionally, individual highway schemes are consulted on with various stakeholders and their view is often incorporated within the design.

In general terms – members of the public can contact us 24 hours a day, seven days a week, through various formats, to provide any comments on the highway network. All carriageway complaints are monitored through the Confirm Customer Service Database.

As technology developments then consultation methods need to adopt to ensure maximum reach to communities and anyone who come into contact with the highway network.

4. Future Demands

This section outlines the anticipated demands that will be placed on the asset over the duration of the plan. These have been considered when formulating the plan and presenting the risks associated with it.

New highway assets are continuing to be added thereby creating an additional need for maintenance and management. The asset is growing marginally year on year due to the adoption of additional roads into the network and through improvement activities such as traffic safety schemes and construction of new road links.

In addition to this our obligations in relation to the drainage network have been significantly increased as a result of the Flood and Water Management Act 2010. The council are the sustainable urban drainage systems approval body. This allows us to manage more closely the potential impact of drainage issues relating to new development schemes.

Traffic growth is monitored on major and ‘A’ class roads by the Department for Transport. There is clear indication that traffic growth on some parts of the road network greatly exceeds that on others with the greatest growth being on the A160 West of Immingham.

Traffic composition is a major factor affecting the rate of deterioration of our highway infrastructure. Where there are heavy wheel loadings the damage and deterioration of the road surface is much greater. The map below is an indication of the Heavy Goods Vehicle traffic flow on the network.

Map of North Lincs showing heavy good vehicles traffic flow

In addition to the need to consider climate change in terms of maintenance methods and materials used there is also the real issue of impact on the carriageway infrastructure of long periods of very wet or dry conditions. These have a particular impact on roads in the Isle of Axholme, which are constructed on a water sensitive base material which, on drying, shrinks significantly and unevenly. This has the effect of significantly reducing the carrying capacity of the road construction and of creating surface alignments that are not consistent with high or medium speed traffic requirements.

Recycling of road construction material during maintenance schemes is a significant part of our contribution to minimising the impact of highway maintenance issues on the environment.

The council is in the process of producing a Green Strategy which will have an impact on all aspects of what the council does. With this will comes new opportunities and challenges in maintaining and upgrading our highway network.

The Highways Team are committed to improving energy efficiency with a view to contribute towards the council objective to be net zero carbon by 2030.

To deliver this objective we aim to reduce the carbon footprint by:

• Following Highways England Guidance and the DFT Transport Decarbonisation Plan
• Incorporating emissions standards into contracts with suppliers
• Environmental considerations and exploiting “new thinking and technology” wherever possible
• Procurement of low carbon surfacing materials. A shift towards using energy efficient materials such as Warm Mix Asphalt (WMA) will need to become the preferred choice of road surfacing
• Use of reclaimed asphalt
• Greater use of carriageway ‘cold’ recycling techniques
• Source energy from renewable sources
• More efficient working to reduce emissions
• Greater use of longer life maintenance treatment processes
• Using energy-efficient lighting for roadsides and signage
• Planting trees for capturing carbon near major projects
• Transition to green fleet
• Battery powered plant and equipment
• Use LED light sources
• De-illumination of traffic signs where regulations permit
• All capital replacements to be LED where possible
• Encourage Walking and Cycling. We need to do things differently, but at the same time ensure that our way forward does not disadvantage those for whom travel by car is the only practical option

5. Service Standards

This section outlines standards what users can expect from the council’s transport assets. It records how these are measured and presents the targets that have been set for the duration of the plan.

The TAMP is based upon delivery of identified service standards. We measure and monitor performance against the service standards in order to determine if the levels of service being provided match up with customer expectations and are in line with both national and local goals and objectives. Therefore, there is a direct link between levels of service, corporate objectives, LTP priorities and funding levels. Publishing these standards enables everyone to understand what they can expect from our highway assets.

The service standards are given in the TAMP and these are set to deliver a road network that allows our residents to be Safe, Well, Prosperous and Connected. Benefitting from a road network that is as fit for purpose as possible within current funding and resource constraints.

October 2016 saw the introduction of ‘Well-Managed Highway Infrastructure: A Code of Practice’. This document is a new combined version of three previous codes of practice. It is important the TAMP follows the recommendations outlined in the Code of Practice.

The code is designed to promote the adoption of an integrated asset management approach to highway infrastructure management based on establishing local levels of service through risk based assessment.

North Lincolnshire has worked with the East Riding of Yorkshire in producing an area wide document, as recommended in the code, and has brought Hull City and North East Lincolnshire on board. The code is now a live document, as of 28 October 2018.

6. Asset Management Practice

This section defines the asset management practices and documentation that the council uses.

The application of good practice and its documentation is essential to the achievement of this plan.

Our asset management policy, the principles of which are, to:

  • Apply asset management systems to manage transport assets
  • Publish a Transport Asset Management Plan
  • Report achievements and performance annually (outcomes)

The systems used to manage our transport assets are set out in the Highway Asset Management Framework. The framework defines how and when we:

  1. Inspect
  2. Categorise and prioritise reactive repairs
  3. Assess condition
  4. Identify and prioritise sites for resurfacing (or reconstruction)
  5. Choose the materials used
  6. Prepare works programmes
  7. Procure and manage works
  8. Record and report costs
  9. Record and respond to customer contacts

Specific investment strategies have been compiled for the major asset groups of carriageways, footways, structures, street lighting, drainage and traffic signals. Each strategy defines how the target service standards are to be delivered. In particular they address the types of works that are planned and state where a “prevention is better than cure” approach has been adopted.

7. Value of the Highway Asset and the financial strategy for its management

This section describes the financial issues associated with asset management practices. Effective financial management and its documentation are both essential to the achievement of this plan.

As of July 2022 the transport asset is valued as shown in the chart below:

Pie chart showing Total Asset Gross Replacement Cost

Total Asset Depreciated Replacement Cost

Typically assets are carried on local authorities Balance Sheet at their market value, which is known as their current value. For property, plant and equipment, where a market exists, this is based on the estimated market value in existing use. For the Highways Network Asset, there is no market and it is not usually possible to sell the asset. For assets where no market exists, the Accounting Code requires the use of depreciated replacement cost (DRC).

Long Term Cost Prediction modelling enables the authority to understand the relationship between future funding needs and resulting condition / performance levels. The level of complexity of each asset model is dependent on the asset data available and the deterioration mechanism used.

The following outlines the asset investment strategies being developed for each of the main asset groups as part of the TAMP;

For the carriageway asset we are concentrating on a process of surface repair where possible and only using deeper strengthening treatments where the carriageway construction has failed. Examination of condition trends and combining this with local knowledge indicates that our unclassified roads are those that need the greatest attention in the short to medium term. We also need to start investing in our B&C road network.

Alongside the maintenance issues there are a number of carriageway infrastructure development schemes either under way or in the pipe line, these being;

  • Carriageway strengthening schemes at C154 Godnow Road, Crowle
  • Reconstruction of CU2 Doncaster Road, Scunthorpe. Berkeley Roundabout to Avenue Vivian
  • Carriageway improvement – C202 Idle Bank, Wroot
  • Resurfacing the A18 Mortal Ash Ebnd Dual Carriageway
  • Significant Package of Resurfacing Works via the Council Members
  • Carriageway strengthening – South Street, Owston Ferry
  • Carriageway Improvement – A1029 Brigg Road, Scunthorpe
  • Carriageway strengthening – A159 M180 to Messingham
  • Carriageway strengthening – A18 High Levels Bank, Sandtoft
  • Carriageway Reconstruction – Highfield Road, Scunthorpe (Hospital to Doncaster Road)
  • Carriageway Improvement – A18 Kingsway (Berkeley Roundabout to Glover Road)
  • Barton Bypass

Principal classified roads where maintenance should be considered Class A roadPrincipal classified roads where maintenance should be considered Class B & C roads

Unclassified roads where maintenance should be considered

Detailed Current Condition (Classified) Roads

The detailed information in the table below is used to report on the national performance indicators for road condition, as shown in the previous graphs. The red condition is the figure used nationally for roads where maintenance should be considered. The figures below indicate where all forms maintenance should be considered on our network red, amber and green.

Performance Indicators – Condition Percentages

12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23
A roads RED 3.4 3.3 2.1 3.1 3.1 3.9 3.0 3.8 2.7 2.5 2.8
AMBER 24.5 23.2 21.5 22.1 22.4 25.1 23.0 23.2 22.3 15.6 16.4
GREEN 72.1 73.5 76.4 74.8 74.5 71.0 74.0 73.0 75.6 82.0 80.8
B roads RED 7.3 8.3 7.1 5.6 5.3 6.3 6.2 7.0 6.5 3.1 2.9
AMBER 35.7 34.2 34.3 33.5 32.7 33.9 36.0 36.5 38.4 23.7 24.4
GREEN 56.9 57.5 58.4 60.9 62.0 59.7 57.8 56.5 51.1 73.3 72.7
C roads RED 9.5 9.7 8.7 8.1 6.1 7.5 9.7 10.6 9.3 6.8 5.6
AMBER 43.5 44.5 36.1 37.6 32.3 36.9 44.6 41.1 37.2 32.2 28.6
GREEN 47.0 55.7 55.2 54.6 61.6 55.5 45.7 48.0 53.5 61.0 65.8
Unc roads RED 39.0 41.0 46.0 41.0 34.0 32.0 28.0 29.0 21.0 21.0 19.0

Carriageway Maintenance Backlog

Calculated Maintenance Backlog (From NLC Scheme Prioritisation Spreadsheet)  A roads

A roads Length Width Area Unit cost Backlog cost
Recon 200mm+ 333 10 3330 150 499500
Resurface 100mm 2992 9 26928 42 1130976
Resurface 40mm 10218 9 91962 21 1931202
Surface Treatment 58750 9 528750 11 5816250
Maintenance Backlog

To make all ‘A’ Class roads maintenance free

£9,377,928
£9,377,928 To improve ‘A Road’ Network by 2% (to net 0%)
£4,688,964 Needed to improve the ‘A Road’ Network a further 1%
£0 To improve the ‘A Road’ Network to the National Average (4%). NLC currently 2%

Calculated Maintenance Backlog (From NLC Scheme Prioritisation Spreadsheet) B roads

B roads Length Width Area Unit cost Backlog cost
Recon 200mm+ 4642 8.5 39457 80 3156560
Resurface 100mm 2433 8.5 20680.5 42 868581
Resurface 40mm 18414 8.5 156519 21 3286899
Surface Treatment 70609 8.5 600176.5 11 6601941.5
Maintenance Backlog

To make all ‘B’ Class roads maintenance free

£13,913,982
£13,913,982 To improve ‘B Rd’ Network by 3% (to net 0%)
£4,637,994 Needed to improve the ‘B Rd’ Network a further 1%
£35,473,183 To improve ‘C Rd’ Network by 7% (to net 0%)
£1,689,199 Needed to improve the ‘C Rd’ Network a further 1%
£49,387,165 To improve ‘B/C Rd’ Network by 6% (to net 0%)
£8,231,194.12 Needed to improve the ‘B/C Rd’ Network a further 1%
£0 To improve the ‘B/C Rd’ Network to the National Average (6%). NLC currently 6%

Calculated Maintenance Backlog (From NLC Scheme Prioritisation Spreadsheet) unclassified roads

Unclassified roads Length Width Area Unit cost Backlog cost
Recon 200mm+ 27596 7 193172 80 15453760
Resurface 100mm 9769 7 68383 42 2872086
Resurface 40mm 207353 7 1451471 21 30480891
Surface Treatment 186406 7 1304842 11 14353262
Maintenance Backlog

To make all ‘Unc’ Class roads maintenance free

£63,159,999
£63,159,999 To improve ‘Unc Rd’ Network by 21% (to net 0%)
£3,007,619 Needed to improve the ‘Unc Rd’ Network a further 1%
£18,045,714 To improve the ‘Unc Rd’ Network to the National Average (15%). NLC currently 21%
Total Highway Work Backlog £121,925,092

From the information we can work out the amount in £’s required in order to treat the sections deemed to require maintenance. Amount £ required to treat the full network and bring up to good condition or a specific point in the carriageways lifecycle. These costs far exceed the amount available hence asset management principals must be followed in identifying the correct treatment for the point in the carriageways lifecycle.

Calculated Maintenance Backlog (From NLC Scheme Prioritisation Spreadsheet)  C roads

C roads Length Width Area Unit cost Backlog cost
Recon 200mm+ 25630 7.2 184536 80 14762880
Resurface 100mm 14707 7.2 105890.4 42 4447396.8
Resurface 40mm 25171 7.2 181231.2 21 3805855.2
Surface Treatment 157286 7.2 1132459.2 11 12457051.2
Maintenance Backlog

To make all ‘C’ Class roads maintenance free

£35,473,183

The carriageway maintenance backlog totals approximately £121,925,092 The total LTP budget for 2023/24 is £12,412,000

Calculated Maintenance Backlog (From NLC Scheme Prioritisation Spreadsheet)

A roads Length Width Area Unit cost Backlog cost
Recon 200mm+
Resurface 100mm
Resurface 40mm
Surface Treatment
Maintenance Backlog

To make all ‘A’ Class roads maintenance free

Similar to carriageways, we utilise a footway prioritisation system that allows identification of specific elements and sections of the footway network where the condition is below standard.

This information, when allied to use and importance of the sections of the footway network allow us to identify and select those sections of footway that are in greatest need of attention.

Footway Backlog

An independent ‘Annual Engineers Inspection’ (AEI) forms the basis of the footway prioritisation system. Appropriate maintenance treatments are recommended for sections deemed below standard. From the specified treatments, it enables the following maintenance backlog to be calculated.

Footways Length Width Area Unit cost Backlog cost
Bituminous Resurface 31,742 1.7 53,961 14 755,460
Bituminous Patch 25,719 1.7 43,722 10 437,223
Flag Replacement 12,980 1.7 20,066 40 882,640
Slurry Seal 604,685 1.7 1,027,965 2 2,055,929
To make all footways maintenance free £4,131,252

There is an ambition to expand our offer to the public for a better and more connected cycling and walking network across North Lincolnshire.

As a council, we have a clear strategic focus to enhance our transport offer to the public. The Integrated Transport Strategy sets out ambitions to transform transport networks to connect people, products and places and support the delivery of the Council’s Key Priorities:

  • Grow the economy
  • Keep people safe and well
  • Enable communities to flourish.

With this in mind, there is a desire to promote active travel across North Lincolnshire, with a key element being cycling in the community. By realising these ambitions, there is significant potential to be catalysts in promoting and enabling healthier and more active lifestyles, as well as, sustainable and environmentally friendly means of travel over the council plan period and beyond.

Sustrans National Cycle Route

National cycle network map

Route 1 passes some of the UK’s most stunning scenery, running in sections from Dover up to the Highlands of Scotland.

Predominantly rural, the 18km section within North Lincolnshire, runs from Barnetby in the south of the region up to the town of Barton and the Humber Bridge. It is shared with the C159 carriageway.

Route 169 of the National Cycle Network, known locally as the Scunthorpe Ridgeway, travels for 8km, north to south through Scunthorpe and passes through green, open spaces with beautiful views of the Trent Valley.

This route was designed to link communities together, providing better access for everyday journeys to schools, local shops and workplaces.

The Ridgeway forms a spinal route through Scunthorpe, from Manor Park in the south through to Normanby Hall to the north of the town. There are plans to link the Ridgeway to the large neighbouring village of Winterton in the future.

Other Cycleways

In addition to the NCR, North Lincolnshire Council Cycle Network comprises of the following.

Type of Cycle Route Total km
Cycle Route (existing) 73.08
Footpaths (existing) 11.06
Off road cycle track/ Shared route (existing) 56.76
On road cycle lane (existing) 15.15
Recreational Cycle Route (existing) 318.27
Right of Way Network (existing) 38.64
Walking The Way To Health (existing) 46.22
Walking Trail (existing) 25.21

Within the next 10 years we plan to build a further 9.8km of new cycleway, and have aspirations for a further 6.7km.

We currently have 1 Parallel Crossing. A further 8 are due to be installed in 2022/23. This will enabling cyclists a safer crossing over some of North Lincolnshire’s busiest roads.

We are currently coming towards the end of a Light Emitting Diode (LED) investment programme. This work is being carried out in conjunction with replacement of lighting units, where this is suitable. This is considerably more energy efficient in reducing maintenance costs.

Current Strategy

The priority in street lighting is to maintain the stock in a steady state and safe condition. In addition, wherever possible, opportunities are taken to invest in the stock to reduce our overall energy consumption.

We have invested in replacement of time expired and faulty lighting columns. This work is being carried out in conjunction with replacement of lighting units, where this is suitable, with modern Light Emitting Diode (LED) units that are considerably more energy efficient and reducing maintenance costs.

Street lighting is maintained in accordance with the recommendations contained within ‘Well-managed Highway Infrastructure: A Code of Practice’.

Cyclic maintenance routes have been established with extended frequencies to match available resources. Data is being collated to support risk based strategy and investment.

It should be noted the lighting stock increases year on year with new developments and highway improvement schemes. There is no increase in funding to support the maintenance of this additional stock.

Reactive Maintenance

The costs for reactive maintenance includes the costs of maintaining street lights, illuminated signs, traffic bollards and school wig wag signs.

Following historic reviews planned service level efficiencies were implemented to align service provision with available budgets. Current service levels are:

  • Night time inspections – None
  • Repair faulty light – Within 5 working days (dependent on location due to cost associated with traffic management on roads like the A18 Mortal Ash Hill.)
  • Cyclic Maintenance – Electrical testing and inspection – as resource permits, (target 6 years)

Planned Maintenance

Capital funding for planned maintenance is aimed at replacing end of life lighting stock and reducing energy consumption. Cyclic structural inspections are carried out on all steel lighting columns in excess of 25 years old. The data from these inspections is then used to prioritise replacements based on condition.

Drainage assets have the problem of some being buried and therefore we may not know exactly what we have, where it is and in what condition it is in. Because of this we are limited to maintaining that which we know about and developing a record of what exists within the highway.

To our knowledge we currently look after,

  • 19 Pump Stations however only 3 are NLC assets
  • 3 Ponds, 1 dry pond and 1currently going through the stage of adoption to the authority
  • 4 Hydrobrakes
  • 3 Swales
  • 3 ditches (aware of presently)
  • 328 Soakaways (approx)
  • 22519 Gullies (approx)
  • 44680 Manholes and catchpits (approx.)
  • 1840km Piped drains (approx.)

We recognise the increased risk of flooding damage and safety issues resulting from water on the carriageway and our plan is to invest in developing a system that more effectively deals with management of drainage issues.

Future Actions

North Lincolnshire Council have contributed significantly to flood risk over the last ten years with many schemes aimed at preventing future flooding to properties within North Lincolnshire.

The Local Flood Risk Management Strategy (LFRMS) was approved in 2016 and published. This document will guide the future flood risk schemes over the next few years. From this document many studies will be required to identify future flood risks.

Since the publication of the LFRMS, the council have carried out approximately 40 major flood alleviation schemes throughout the district. These schemes have ranged from new high capacity highway drainage systems, upsizing of significant ditches and culverts, installation of robust flood banks, strategically placed flood bunds and walls to divert flows, and reshaping/renewing highways to control the flow of water away from properties.

The LFRMS is due for update this year, however EA are currently redeveloping their UK flood models in order to consider the latest data with regards to climate change and it’s effects. It is therefore likely that the existing LFRMS will receive a light touch update this year with a full review of the document likely to take place in 2024 when the latest model data is available.

The Scunthorpe Surface Water Management Plan (SWMP) Phase 3 has been developed for the 3 highest risk locations identified. 4 options have been developed to mitigate flooding for the following 3 areas:

  • Scunthorpe General Hospital
  • Baldwin Avenue/Ellison Avenue, Bottesford
  • Warley Road, Scunthorpe

The proposed way forward is ongoing with Severn Trent Water on what is most economically beneficial and deliverable in the near future.

Our long term strategy with our structures asset is to maintain them such that significant costs do not arise there are instances – as at present – where a bridge on a strategic route is showing signs of distress and requires urgent attention. Currently our main issue is with the A18 railway bridge just to the west of Humberside Airport. This is on a section of the A18 that provides a critical connection between the airport and the strategic road network at Junction 5 of the M180.

In order to deliver this strategy the structures team have a programme of works which includes:

  • Maintenance painting
  • Safety improvements at high risk bridge sites
  • Structural improvements to avoid bridges becoming obsolete
  • Replacement of damaged and ineffective expansion joints
  • Condition intervention – general maintenance works necessary to prevent further deterioration of the stock.

Current Condition

The current, and historic, condition of the structures stock is demonstrated in the following table. BSCI is the Bridge Stock Condition Indicator which provides an overview of the condition of the bridge stock. BSCI values are published as average values for the stock as a whole and for the “critical” elements of the structures stock. A value of 100 indicates that the entire stock is in good condition and as the index reduces towards zero then the condition also reduces.

*Sample only in these years, not full results.

In line with the CSS Bridge Group document – BCI Vol 3: Evaluation of Bridge Condition.
Indicators, our stock condition value lies between 65 and 84 indicating that the overall condition of our asset is FAIR with the A18 Melton Ross Bridge being in such a condition as to require replacing.

BSCI 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21
Structures BSCI (ave) 89* N/A N/A 80 N/A 77 77 77 77
Structures BSCI (critical) 80* N/A N/A 76 N/A 71 71 71 71

Structures – Major Maintenance Programme (since 2017)

Asset name – scheme description Parish Estimated Cost (as at 2016) Intervention Date Maintenance Details Outcome if Intervention Not Taken
A18, Wrawby Railway Bridge – Side Arch Infilling Wrawby £350,000 2017 Removal of historic partial infilling of side arches and infilling with foamed concrete Introduction of weight limit (possibly 7.5T)
A 18, Melton Ross Railway bridge – replacement Melton Ross £7,000,000 Full replacement of existing bridge and approaches Reintroduction of 7.5 T weight limit on A18, possibly reducing with time, long diversion route
A 161, Crowle flyover – bearing replacement Crowle £350,000 Full replacement of all bridge bearings and bearing plinths Risk of loss of proper support to bridge deck causing structural damage to deck possibly requiring closure of
A161 or weight restriction
A18, Glanford Bridge – repainting Brigg £100,000 2020 Repainting of all structural steel elements of
the bridge deck
Rusting will cause deterioration of the
structural steel requiring repair work
prior to future repainting
A15, Bonby Lodge Bridge – rewaterproofing and joint replacement Bonby £100,000 2025 Replacement of the deck waterproofing membrane and the movement joints Ingress of de-icing salts through the
deteriorated waterproofing and joints will damage the concrete deck of this bridge
A15, Horkstow Bridge – rewaterproofing and joint replacement Barton £130,000 2026 Replacement of the deck waterproofing membrane and the movement joints Ingress of de-icing salts through the
deteriorated waterproofing and
joints will damage the concrete deck of this bridge
A18, Melton Ross Railway Bridge – Demolition of Existing Bridge Melton Ross TBD TBD Removal of redundant bridge On-going maintenance responsibility for redundant structure over railway

We hold a comprehensive Traffic Signal Inventory which is constantly updated. From this we can develop schemes based on the information obtained. So far we have identified schemes for the oldest asset, most frequently maintained and are currently working towards identifying options for better connectivity and communication between sets of signals to improve traffic flows.

The overall priority is to ensure traffic signal equipment is maintained in a steady state and safe operational condition. In addition, the equipment is operated to minimise delays and to respond to incidents that occur on the highway network.

We have a collaborative working partnership with North East Lincolnshire Council for the maintenance of Traffic Signals.

New technology is being utilised to improve efficiency of operations such as LED signal aspects and above ground detection equipment.

Signalised Junctions and Pedestrian Crossings:

The intention is to replace traffic signal installations at 25 years old due to the deterioration of electrical and structural components.

When an installation reaches 20 years of age it is assessed to determine if:

  • a partial refurbishment is required to keep the installation operational for another 5 years
  • a full refurbishment is necessary at 20 years
  • intervention is required before it is 25 years old

In organising the planned works programme, a one year detailed programme is produced plus a 5 year programme to assist with planning funding requirements and to take advantage of shared projects (e.g. development schemes) to reduce costs.

The assessment of the priorities for future work includes consideration of the asset condition data collected during annual inspections.

In previous years there has been significant growth in the signals stock. There are also existing stock that will be due for replacement over the next few years. In more recent years the economic climate has meant that the stock has remained static as there has been very little increase in new signals. However, it is anticipated that with increased economic activity in North Lincolnshire the stock may increase further adding some pressure to routine maintenance budgets.

Active Travel

Additional Traffic Signal equipment is anticipated as North Lincolnshire looks to promote Active Travel. As part the Councils aim to improve peoples health and wellbeing we will seek to provide more Walking and Cycling facilities throughout the authority.

At present we are not working on a strategy to cover the street furniture assets in the short term.

They are currently being maintained with available funds. A strategy for data inventory collection will be required as this forms part of the Whole Government Accounts and Asset Management Guidance, key topics.

8. Risk Management

Risk management and control is essential to the effective delivery of this Plan.

The Corporate Risk Management Strategy sets out how the council manages risk corporately.

This strategy is also applied to managing the council’s transport assets. A risk register is compiled for the risks associated with the transport/highway asset. The methods used to create and manage this transport risk register are set out in the asset management manual. The highest rate risks that were considered when compiling this plan are shown in the table below.

The risks that could prevent the achievement of the targets set by this plan are:

Plan Assumption Risk Action
The plan is based upon winters being normal Adverse weather will create higher levels of defect occurrence and deterioration than have been allowed for Budgets and predictions will be revised and this plan updated if abnormally harsh winters occur
Available budgets are as assumed External pressures may mean that government will reduce the funding available for highways Re-assess budget allocation annually to reflect external pressures. Prepare business cases
to request additional funding from other authority budgets
Construction inflation will steadily increase Exceptional inflation of construction costs may increase the cost of works (particularly oil costs as they affect the cost of road surfacing materials) Re-assess budget allocation annually to reflect external pressures. Prepare business cases
to request additional funding from other authority budgets
Levels of defect occurrence and deterioration are based on current condition data Continuing collection of condition data may identify that asset condition is worse than predicted and the investment required to meet targets may be insufficient Re-assess budget allocation annually to reflect improved extent of condition data
Resources are available to deliver the identified improvement actions Pressures on resources may mean that staff is not allocated to service improvement tasks Monitor the situation regularly and advice council accordingly

9. Funding Allocations

This section outlines existing funding and future funding streams from government. Effective financial management and its documentation are both essential to the achievement of this plan.

The LTP funding allocations identified are as follows:

2022 LTP AllocationNote: Surface Treatments includes work on the Principal Road Network (PRN) and the Non Principal Road Network (NPRN). It comprises of reconstruction schemes, surface dressing, micro asphalt, plane and inlay and recycling schemes.

The above chart relates to the LTP funding allocations. There are further funding sources that are used, where possible, to fund other transport / highways related issues. In addition to this the council has committed capital funding specifically for larger highway construction schemes, drainage and flood defence, street lighting works and general highway works, including pothole repair.

Future funding will now be determined by two methods

  • Highways Maintenance Funding Formula (Needs Based Formula) + Incentive Funding
  • Internal Council allocated funding

The Department for Transport (DfT) have presented multiyear funding figures. The tables below show this Highway Maintenance Funding Formula along with the possible money available subject to which “Band” North Lincolnshire fits into, for the incentive funding element.

The incentive funding element is produced from a self-assessment ranking questionnaire that is to be presented to DfT on an annual basis. There are three possible “Bands”. North Lincolnshire Council was a “Band 3” at the time of submission for the deadline of March 2022.

Local Authority Pothole Funding 2022 – 2025 Highway Maintenance Block Needs Element 2022 – 2025 Highway Maintenance Block Incentive Element 2022 – 2025 HM Funding Network North Annual total
North Lincolnshire £5,553,000 £2,553,000 £638,000 £750,000 £7,662,000

10. Collaborative Working

North Lincolnshire and the East Riding of Yorkshire Council have implemented a single shared Code of Practice for Well Managed Highways. It is hoped to extend this code to cover street lighting and structures in the future.

North Lincolnshire and North East Lincolnshire currently have a framework for the collection of highway survey data and are also working closely together on the whole government accounts aspect of the highway asset.

11 Conclusions

Significant progress has been made by North Lincolnshire Council in delivering the actions identified in the Transport Asset Management Plan.

Systems are in place to monitor the long term condition of all key assets and plans are in place to maintain these at an appropriate condition which reflects the funding available.

The continuing deterioration in the condition of our minor roads and particularly the unclassified road network is still a concern, while significant progress has been made in improving the condition of this part of the network, it will still require significant additional funds in the short to medium further improve condition. In the short term budgets have been prioritised and reallocated to support the increase in preventative maintenance, like surface treatments, but there are now a number of larger, more expensive, structural repair schemes that also need attention and are higher spending treatments.

Large development in North Lincolnshire, such as the Lincolnshire Lakes development will bring increased population growth, business and money for the area but will have a significant impact on the highway asset, all of which will need to be maintained in the medium to long term.

The council is in the process of producing a Green Strategy which will have an impact on all aspects of what the council does. With this will comes new opportunities and challenges. The Highways Team are committed to improving energy efficiency with a view to contribute towards the council objective to be net zero carbon by 2030.

North Lincolnshire Council has a robust TAMP which is supported by well-developed systems and data which helps ensure that the available budgets are spent effectively.

The continued support of Members is essential in identifying appropriate funding, over and above existing government grants for the highway asset is vital to enable it to remain in a steady state of maintenance or ideally improve on its current condition.