Street Work Permit Scheme

The North and North East Lincolnshire permit scheme

The North and North East Lincolnshire permit scheme [509Kb] is intended to deliver public benefits by minimising the inconvenience and disruption caused by road works to all road users.

Anyone intending to carry out work on certain streets must apply for a permit which sets out how the work must be undertaken to minimise disruption. This includes works by utility companies and works carried out by North Lincolnshire Council and its partners. It does not include activities such as builders’ skips and scaffolding.

The current scale of permit fees that apply is included in the North Lincolnshire Council permit fees section below:

For advice on the permit scheme or to discuss any immediate activity you may be undertaking please contact us on network.management@northlincs.gov.uk or call 01724 297000.

The North and North East Lincolnshire Permit Scheme Order 2018

North Lincolnshire Council (‘The Council’) acting as the Local Highway Authority approves the permit scheme referred to as ‘The North and North East Lincolnshire Permit Scheme’ and in exercise of its power conferred by Section 33A (2) of the Traffic Management Act 2004, the Traffic Management Permit Scheme (England) (Amendment) Regulations 2015 and of all other enabling powers makes this Order.

The Council Permit Scheme came into effect on 3 January 2018.

Permit scheme evaluation 2020 [PDF, 788Kb]

The fee levels that apply from 3 January 2018 are shown below:  These take account of the revised fee structure set out in the additional advice note issued by the DfT in January 2013 for North Lincolnshire Council.

 

Provisional Advance Authorisation

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £98

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £68

 

Major Activity Permit – 0 to 3 days

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £62

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £42

 

Major Activity Permit – 4 to 10 days

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £114

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £72

 

Major Activity Permit – 10 days+ or requiring TRO

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £206

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £127

 

Standard Activity Permit

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £114

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £72

 

Minor Activity Permit

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £62

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £42

 

Immediate Activity Permit

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £58

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £40

 

Variation to permits

Permit Fee Cat. 0 – 2 or Traffic Sensitive: £45

Permit Fee Cat 3 & 4 Non-Traffic Sensitive: £35

 

Details of discount for works on traffic-sensitive streets wholly outside traffic-sensitive times

We offer a 30% discount for works in traffic-sensitive streets where those works take place wholly outside traffic-sensitive times (in accordance with Amendment regulation 12 (b) which amends regulation 30).