Update on scheme
This scheme is well underway, with internal walls being erected in parts of the building.
Progress on site as of 30 November 2010:
- Roof complete, building watertight
- Brickwork complete
- Windows substantially complete
- External insulation/render 40 per cent
- Metal stud partition walls 85 per cent
- Decorations underway
- Joinery well advanced in blocks C and D
- M&E first fix in all trades well advanced, second fix underway
- Power on December 2010.
The school has signed off many drawings that include the furniture, fittings and equipment (FF&E) to the new school.
Completion dates
Target handover date of new build - June 2011
Demolition of the old school buildings - starts summer 2011
Handover of external works (including all weather pitch) - February 2012
Please find attached current school plans. The documents give a more in depth overview of the school's design options.
Artist's impressions
)
Please note: due to the detail of the plans, the file size of the above documents is quite large and may take some time to download.
Background information
On 4 December 2006, the School Organisation Committee (SOC) unanimously decided to approve the proposals to merge both South Leys Business and Enterprise College and Thomas Sumpter School - A Specialist College in English and Media Arts. The merge took place on 1 September 2007 and the new school was named Melior Community College for Business, Enterprise and the Arts. Once the new Melior Community School is built all pupils would be transferred. The target date for the new community college is on, or before, summer 2010.